Open Roads Sooner with Concrete Curing Sensors

completed road
completed road

Road construction can be a lengthy, disruptive process—so ensuring that your project stays on schedule is one of your most important responsibilities as a project manager.

Get Your First SmartRock Concrete Sensor for FREE

Giatec SR demo kit_
Giatec SR demo kit_

Even before groundwork can be begin, the planning stages of some roadways require months of soil analysis by engineers. Public consultation can also be a factor in road-building plans that pushes back schedules. While they do take time to complete, these activities are crucial in defining the scope of the project and assessing potential risks.

Once the planning stage is complete, contractors bid on the job. With a winning bid selected, further land surveying begins. Geographical obstacles are removed, and the foundation of the roadway can be cut, filled, and compacted with different layers of soil and aggregate material. This process ensures that the pavement will have a stable surface to sit on.

At this point, drainage systems and electrical infrastructure can be put in place before the pavement material is laid.

Asphalt is the chosen pavement material for many road construction projects due to its low cost—but concrete is becoming increasingly popular for a number of reasons:

  • Concrete is rigid, so it withstands greater traffic loads for longer.
  • Concrete is more weather and chemical resistant than asphalt.
  • Asphalt’s binding ingredient is bitumen—which is derived from crude oil and releases toxic chemical fumes as it cures. Concrete has less of a negative impact on the environment.
  • Concrete’s overall superior durability means much lower maintenance costs over time and longer life cycles for finished roadways.

In short, concrete roads are a better long-term investment.

Open Roads Sooner with Concrete Curing Sensors

What About Testing for Monitoring Concrete Pavement Strength?

Concrete Break TestOne thing traditionally seen as an obstacle to the use of concrete is the need for concrete cylinder testing. This requires samples of various mix designs to be cured and tested for compressive strength, as outlined by ASTM C39 and AASHTO T 22 Standard Method of Test for Compressive Strength of Cylindrical Concrete Specimens.

Whether these samples are cured onsite or in a laboratory, they need to be tested in a third-party lab. As a project manager, this reliance on a third party can be frustrating as the lab’s testing schedule is completely out of your control. Several steps in the testing process – such as waiting for samples to be picked up, for the tests to be run on them, and for results to be communicated – can create significant delays for your crew.

According to Plangrid and FMI, 35% of construction professionals’ time (over 14 hours per week) is spent on non-productive activities including looking for project information, conflict resolution and dealing with mistakes and rework.

In the already unpredictable world of construction, adding the additional variable of a third-party concrete testing lab can feel like a significant sacrifice. This can push a lot of contractors building roads to choose the cheaper—albeit shortsighted—solution of paving with asphalt.

But there’s a better way.

Concrete Maturity Strength Testing for Pavement Using Curing Sensors

Maturity is a non-destructive approach to concrete testing that allows you to estimate the early-age and compressive strength of in-place concrete in real-time. Adopting the maturity approach in your jobsite eliminates the need for concrete cylinder break tests, allowing you to greatly optimize your schedule.

ASTM C1074 is the standard for concrete maturity, while AASHTO T 325—Standard Method of Test for Estimating the Strength of Concrete in Transportation Construction by Maturity Tests—provides procedures for estimating concrete strength in roads, bridges, and other transportation structures through the use of a maturity index.

Both standards require mix design calibration for maturity testing. ASTM and AASHTO have slightly different calibration (ASTM C511 vs AASHTO T 276), so make sure you are aware of which standard applies to you based on your location. Each state has its own Department of Transportation with unique specifications, so be sure to familiarize yourself with any applicable rules.

After your concrete mix is calibrated for maturity testing, you can use wireless concrete curing sensors to test the maturity of your in-situ slab and monitor the strength of your poured concrete onsite and in real-time!

How Will the Maturity Method Save You Time on Pavement Projects?

Opening roads to traffic after construction is complete is one of the highest priorities in terms of meeting project deadlines. Even opting for lane closures can be extremely expensive due to costly penalties for delays. In short, the sooner you can open roads, the better!

The U.S. Department of Transportation Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-14 states that new or restored roads can’t be opened to traffic sooner than 14 days after the slabs have been placed unless they reach a compressive strength of 4,000 pounds per square inch (28 MPa).

If—before your slab is poured—you install SmartRock® sensors on the formwork, you and your crew will be able to monitor the strength of your concrete in real-time as it cures, using the SmartRock Mobile App. Depending on your mix design, this could enable you to open roads to traffic much sooner.

As of 2017, the Colorado Department of Transportation requires maturity testing for the opening of bridge decks and concrete pavement to traffic. In Alabama, Florida, Idaho, Iowa, Kansas, Minnesota, Missouri, Montana, New Mexico, North Carolina, North Dakota, Ohio, Oklahoma, Oregon, Pennsylvania, Texas, Utah, Virginia, Washington, West Virginia, and Wisconsin maturity testing is becoming a normal requirement across many applications.

Concrete Pavement Strength Monitoring with C.L. Heilman

C.L. Heilman began work on a major new interchange north of Coeur d’Alene, Idaho. The project involved a 138 foot, four-lane bridge spanning the U.S. 95 and a two-lane, 250-foot bridge spanning the Union Pacific railroad track.

“It’s always been an option to use the maturity curve, but in 2018 the Idaho Transportation Department made it mandatory for Highway Construction projects to perform maturity testing in accordance with ASTM C1074 to confirm compressive strength for form removal and loading,” says James Heilman, co-owner and VP.

Heilman estimates that SmartRock saved half-a-day pour for every pour that was on the “critical path.” The IDT interchange project involved over 20 pours. Over a two-month period, Heilman says “I’d say we shaved five-to-ten days off the schedule by using SmartRock…and completed the work 10 to 15 percent faster.”

Take Control of Paving Projects

If you build concrete roads, you’ve undoubtedly experienced project delays because of concrete cylinder testing. Switching to testing concrete strength with SmartRock and the maturity method will enable you to obtain data regarding the curing and hardening of your concrete element—onsite or remotely, in real-time.

From the moment your crew pours the project’s first slab, you’ll have access to all the information you need to open roads to traffic ahead of schedule.

*Editor’s Note: This post was originally published in June 2020 and has been updated for accuracy and comprehensiveness. 

Leave a Reply

Your email address will not be published.

Related Articles

New Giatec 360 Updates – Part 2: Graph Customization Tools

This article will continue on the topic discussed in Part 1, be sure to check it out! Get Your First SmartRock Concrete Sensor for FREE Free Demo Kit Display The max and min temperature limits can be assigned to a sensor using the Parameter Thresholds function on both the app and the web platform of Giatec 360. When assigned, these limits are represented in the form of fine lines in red (max limit) and blue (min limit) color.  Using the 360 dashboard, a user can choose…

New Giatec 360 Updates – Part 1: Temperature, Strength, and Maturity Charts

As part of Giatec’s continued efforts and goal to meet customer requirements and expectations, progressive changes are being made to the system to better comply with updating needs. Working with clients on a global scale, we strive to provide a streamlined platform that is one place for all. With the feedback collected from our valued customers several updates and transitions have been made to the Giatec 360 program, especially the ‘Charts’. To learn what the updated site has to offer and how beneficial this can be…

Giatec Family Laptop Top Down

Level Up Your Project Reports With Giatec 360™ – Part 2

Let’s dive deeper into report generation to learn more about how Giatec 360’s reports help you make better decisions faster on the jobsite. For an introduction to Giatec 360, click to read Part 1 of this blog. Get Your First SmartRock Concrete Sensor for FREE Free Demo Kit Giatec 360 – An Overview Some of the key features are as listed as follows:   Temperature Differential Analysis  Generating Full PDF/CSV Reports  Customizing the reports as per user’s preferences which includes   Generating reports for a specific data range …

Claim Your Free Demo Kit