Concrete testing methods differ from place to place and each country has their own specifications that must be followed. While engineers and project managers in America adhere to the American Standard Testing Method (ASTM) C39 / C39M , Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens, those residing in Britain adhere to the standard BS EN 12390, Testing hardened concrete, Compressive strength of test specimens, outlined by the British Standards Institute.
Like the cylinder break test, the concrete cube test is performed for the purpose of determining the compressive strength of a concrete element. The cubes used for this test have a dimension of 150 x 150 x 150 mm as long as the largest aggregate does not exceed 20 mm. Generally speaking, the cubes are cured for and tested at 7 and 28 days, although certain projects might require curing and testing times of 3, 5, 7, 14, or more days. The results from the compressive strength test are used to determine the strength of the concrete. If the test results are inconclusive or show that your concrete isn’t curing as quickly as it should, you risk not being able to advance your project as soon as you would like to.
What is the Standard for Concrete Cube Test?
Standards for different methods of concrete testing are either governed by the British Standards Institute or by the client. They outline all the aspects and details required to carry out the tests and ensure they are properly performed. QEM Solutions outlines the standards for concrete cube testing as follows:
A list of the National Concrete Standards relevant to Cube Testing are:
Hard Concrete: BS EN 12390-1:2012 – Shape, dimensions and other requirements for specimens and moulds BS EN 12390-2:2019 – Making and Curing Specimens for Strength Test BS EN 12390-3:2019 – Compressive Strength of Test Specimens BS EN 12390-4:2019 – Compressive Strength – Specification of Test Machines
The Concrete Cube Test Formula
When it comes to testing the compressive strength of any material, the formula goes as follows:
Compressive Strength = Load / Cross-sectional Area
This breaks down as the load applied at the point of failure to the cross-section area of the face on which the load was applied.
The Procedure for Testing Concrete Cube Compressive Strength
Performing a test for the compressive strength of a concrete cube consists of a few steps. First off, the concrete being tested is poured into a mould meeting the size requirements mentioned above — 150 x 150 x 150mm. Second, the concrete is appropriately tempered to remove any voids or gaps in the concrete. Then, after 24 hours of curing, the test specimens are removed from the forms and put into curing baths to regulate the curing period. Once the specimens have been cured for the duration outlined in the project specifications, the surface of the specimens is made smooth and even. The specimen is then put into a compressive strength testing machine and gradually put under load at the rate of 140 kg/cm2 per minute until the specimen fails. While tests are required in the project specifications to ensure the safety of your concrete element, concrete cube tests can be time consuming and can delay your project timeline.
The good news is that project managers and engineers don’t need to rely solely on concrete cube tests during their projects. Companies like Hunnu Concrete LLC have improved their concrete testing accuracy by using SmartRock® wireless concrete maturity sensors.
Although concrete cube tests might still be required in your project, you can use these concrete sensors to cut timelines and gain more confidence in your test results. As demonstrated in this case study, thanks to the wireless temperature and strength sensors, Hunnu was able to accurately track all data. This meant that when temperatures continued to increase by 5 degrees they knew right away when to add cold water to the concrete to decrease temperatures. With the help of SmartRock, they were able to hold the temperature of the in-situ concrete at 70 degrees Celsius for the remainder of the project and ensured consistent curing and strength development.
If you regularly use concrete cube testing, you may be used to the patience it requires, and the delays from third-party. The reality is, those delays can be costly and are no longer necessary. The methodology behind the concrete cube test has been used on jobsites since the 19th century. Despite that, little to no progress has been made to speed up the testing process. However, thanks to innovative technology and research, there are other ways to test the strength of your concrete that don’t include destructive methods.
Ottawa-based company, Giatec Scientific Inc., is revolutionizing the construction industry by bringing smart concrete testing technologies and real-time data collection to the forefront of every jobsite.
Learn more about Giatec Scientific Inc Mission and Core Values, or read more about Giatec Scientific's Line of Products.
We are bringing long-overdue change to a conservative industry by addressing the current challenges in concrete testing, analysis, design, and production. Click the following links to learn more about Giatec Scientific's Management Team and Research and Development Team.
Ottawa-based company, Giatec Scientific Inc., is revolutionizing the construction industry by bringing smart concrete testing technologies and real-time data collection to the forefront of every jobsite.
Learn more about Giatec Scientific Inc Mission and Core Values, or read more about Giatec Scientific's Line of Products.
We are bringing long-overdue change to a conservative industry by addressing the current challenges in concrete testing, analysis, design, and production. Click the following links to learn more about Giatec Scientific's Management Team and Research and Development Team.
Please give me some idea of when cubes must be taken on site and when not. I would be very grateful for your advice. Are cube samples necessary for all types of foundation? ie.piles, strip footings,ground beams,pads,rafts etc etc. Likewise for ground supported slabs, concrete frame elements ie. Columns,beams and upper floors. Also concrete solid walls. I was told cubes are not necessary for all such elements. Is that correct please. I am a student and will soon join a national contractor. I may be using your services in the near future. Regards, Nick.
Hello Nick, in general, every structural concrete pour must be tested for acceptance. However, there is a clear distinction between acceptance testing (at 28 days) and testing for formwork removal. The latter is only necessary when formwork must be removed for project continuation. It would be highly unpractical to have to wait 28 days to remove formwork of every pour. You can imagine how much time it would take to build a high-rise building if every pour were separated by 28 days. For this reason, the field testing (cube or cylinder) method can be applied to monitor the concrete strength evolution. As such, the time at which the structure will be able to support itself (dead load) can be estimated to remove the formwork in advance (i.e. after 7 days with a minimum specified strength, usually 15MPa depending on type of structure, service conditions, concrete mix-design, etc.) to allow for faster completion of the work. Overall, testing for formwork removal is case dependent. Its necessity is based on the element itself, its project, its schedule and its location (note that standards vary between countries for example). On the other hand, testing for acceptance is necessary in most cases, as it is crucial to know if the concrete is up to specifications. Otherwise, there would be no way of knowing when an error occurs, and the structure/project could be at risk. Overall, cube testing with field curing depends on the case, whereas cube testing with lab curing (acceptance) is necessary. For the differences between the two types of curing, visit the following blog: https://www.giatecscientific.com/education/field-cured-vs-standard-cured-cylinders/. Also, our company specializes in the replacement of outdated testing method, such as the field curing testing. We offer innovative procedures, accepted in the standards, to allow for easy and constant monitoring of the concrete strength. Please refer to the following to blog for more information on how field-curing can be properly replaced: https://www.giatecscientific.com/education/avoiding-the-uncertainties-of-concrete-cylinder-testing-with-the-maturity-method/. Hope this answers your question!
The maturity method is a convenient approach to predict the early age strength gain of concrete, using the principle that the concrete strength is directly related to the hydration temperature
How to Test and Check Concrete Temperature?Like with many other materials, concrete can change in quality as a result of its temperature. This is especially important when there are certain…
With traditional concrete strength testing practices, that is the use of cylinder break tests, the reliance on third-party testing labs is detrimental to a project’s timeline and budget. While wired…
We use cookies to provide you with a better experience, analyze site traffic and assist in our marketing efforts. By continuing to use this website, you consent to the use of cookies in accordance with our Privacy Policy Page.
2 Responses
Please give me some idea of when cubes must be taken on site and when not. I would be very grateful for your advice. Are cube samples necessary for all types of foundation? ie.piles, strip footings,ground beams,pads,rafts etc etc. Likewise for ground supported slabs, concrete frame elements ie. Columns,beams and upper floors. Also concrete solid walls. I was told cubes are not necessary for all such elements. Is that correct please. I am a student and will soon join a national contractor. I may be using your services in the near future. Regards, Nick.
Hello Nick, in general, every structural concrete pour must be tested for acceptance. However, there is a clear distinction between acceptance testing (at 28 days) and testing for formwork removal. The latter is only necessary when formwork must be removed for project continuation. It would be highly unpractical to have to wait 28 days to remove formwork of every pour. You can imagine how much time it would take to build a high-rise building if every pour were separated by 28 days. For this reason, the field testing (cube or cylinder) method can be applied to monitor the concrete strength evolution. As such, the time at which the structure will be able to support itself (dead load) can be estimated to remove the formwork in advance (i.e. after 7 days with a minimum specified strength, usually 15MPa depending on type of structure, service conditions, concrete mix-design, etc.) to allow for faster completion of the work. Overall, testing for formwork removal is case dependent. Its necessity is based on the element itself, its project, its schedule and its location (note that standards vary between countries for example). On the other hand, testing for acceptance is necessary in most cases, as it is crucial to know if the concrete is up to specifications. Otherwise, there would be no way of knowing when an error occurs, and the structure/project could be at risk. Overall, cube testing with field curing depends on the case, whereas cube testing with lab curing (acceptance) is necessary. For the differences between the two types of curing, visit the following blog: https://www.giatecscientific.com/education/field-cured-vs-standard-cured-cylinders/. Also, our company specializes in the replacement of outdated testing method, such as the field curing testing. We offer innovative procedures, accepted in the standards, to allow for easy and constant monitoring of the concrete strength. Please refer to the following to blog for more information on how field-curing can be properly replaced: https://www.giatecscientific.com/education/avoiding-the-uncertainties-of-concrete-cylinder-testing-with-the-maturity-method/. Hope this answers your question!