Seattle Concrete Tunnel Project is Beginning to Take Shape

Portions of the vast Highway 99 tunnel are starting to look like the double-decker thoroughfare that former Gov. Chris Gregoire promised seven years ago. Bertha’s recent progress along the Seattle waterfront — some 1,500 feet since diving below the Alaskan Way Viaduct on April 29 — has allowed crews to pour concrete walls and foundations for road decks. The giant tunnel-boring machine is currently stopped for inspection and replacement of some of its 75-pound steel cutting teeth, below Spring Street just west of First Avenue.

Meanwhile, workers at Seattle Tunnel Partners (STP) are slowly extending the decks north from the south portal in Sodo. First, they drill holes in the 57-foot diameter tube, and insert U-shaped pieces of rebar steel on each side. These help to anchor and fasten larger cages of rebar that form the skeleton of the deck foundations. Red gantry cranes bring forms that are lowered around the cages, creating a shape where fresh concrete is pumped in. It hardens into ledges that support the walls. The upper or southbound deck is poured first, fastened to the walls. About 600 feet of deck has been built so far, a Washington State Department of Transportation update said Wednesday.

After Bertha is finished digging, hundreds of precast panels will be brought in from Tacoma to make the northbound decks. These are a lean 8 by 32 feet, so they will need to be spun a quarter-turn inside the tunnel, and set crosswise on the ledges. STP project director Chris Dixon wouldn’t predict Wednesday how soon the job would be done. In the contractors’ last statements, Bertha was supposed to emerge at South Lake Union in December, and the 1.7-mile toll tunnel open for traffic in April 2018, but those milestones are likely to slide several weeks. The state transportation department and STP originally aimed to finish in December 2015, when the $1.35 billion contract was signed in early 2011. Two years were lost to front-end damage to the tunnel-boring machine and repairs.

This week, workers continue to check the cutting bits, working in brief shifts underground at under 2½ times atmospheric pressure. Only 33 of more than 400 bits examined to date have been replaced, Dixon said — a sign that clay soils under mid-downtown aren’t causing risky abrasion. In fact, STP this spring removed dozens of dual-disc cutting tools that crack boulders, and replaced those with ordinary dirt scrapers, Dixon said.

No boulders have appeared lately, Dixon said, but they could show up in shallower soils when Bertha resurfaces near Aurora Avenue. Digging 40 feet or more per day, “we have no concerns whatsoever” about Bertha’s ability to reach the finish line, which awaits 6,235 feet ahead, he said.

99 Tunnel

Source: http://www.seattletimes.com/seattle-news/transportation/highway-99s-tunnel-double-decker-begins-to-take-shape/

Photo Credit: Ken Lambert/The Seattle Times

Leave a Reply

Your email address will not be published. Required fields are marked *

Related Articles

SmartRock Sensor and Mobile App

The Importance of Monitoring Temperature Differentials in Mass Concrete

Closely monitoring concrete temperatures is critical for ensuring proper strength development of concrete structures, regardless of their application or size. However, when it comes to mass concrete structures, temperature differentials also need to be considered due…

SmartRock

The Best Concrete Thermometers in 2021

You’ve arrived at this blog post because you’re interested in evaluating and selecting from the plethora of concrete testing thermometers available in the market. Before we dive into suggesting some of the best thermometers we’ve come across, it is essential…

An Essential Guide to Concrete Formwork Removal

Before we delve into the process of its removal, it is essential to understand what “formwork” means in the concrete sphere. As described by Hunker, formwork that is set prior to pouring concrete “serves as a frame for the shape of the concrete, holding…

completed road

Open Roads Sooner with Concrete Curing Sensors

Road construction can be a lengthy, disruptive process—so ensuring that your project stays on schedule is one of your most important responsibilities as a project manager. *For eligible new customers only Get a Free Trial Kit…

Worker Pouring Concrete

Pouring Concrete in Winter vs. Summer: What’s the Difference?

One of the most important aspects of concrete strength development and ensuring the integrity of a completed structure is the temperature of the concrete pours during the early stages of construction.  *For eligible new customers only…

We use cookies to provide you with a better experience, analyze site traffic and assist in our marketing efforts. By continuing to use this website, you consent to the use of cookies in accordance with our Privacy Policy Page.